In LAYOUT FINALISATION, which of the following is not the Secondary Details :-
Future expansion of switchyard should be easily possible
In seismic prone zones height of structures should be as low as possible.
Location and Orientation of Main Entry of Switchyard
The outgoing transmission line should not cross each other
For Field Test , Significant depth of Exploration For isolated fdn :
0.5 to 1 times the width
1.5 to 2 times the width
2.5 to 4 times the width
None
For Field Test , Significant depth of Exploration For Pile fdn :
1m to 5m
5m to 15m
20m to 35m
In reamed piles type of Deep Foundations :-
are constructed to a depth of 1 to 3m into the ground
are constructed to a depth of 3 to 8m into the ground
are constructed to a depth of 10 to 18m into the ground
None
In Friction piles type of Deep Foundations :-
Terminated at Lower depth
Terminated at Higher depth
Terminated at Average depth
None
What is the MINIMUM REQUIREMENT of Contour survey extending outside the boundary wall on all sides :
up to at least 2 m
up to at least 5 m
up to at least 10 m
None
Which of the following is not the type of Substation Structure :
Gantry Structure–DP / Lattice
Outgoing Feeder–RSJ Pole (DP)
Road / River Crossing RSJ / Tubular / Lattice
Equipment Support Structure –DP / Lattice
Which of the following is not the type of Line Structure :
DTR Structure –SP / DP PSC / RSJ / Tubular
Equipment Support Structure –DP / Lattice
Road / River Crossing RSJ / Tubular / Lattice
None
Which of the following is not correct for Pole Structures :
The pole shall be erected such that minimum 1/6th of the total length of the pole shall be embedded into the ground surface
Orientation of Poles structures shall be according to the loading or stringing direction
The loading on the poles can be exceeded its design capacity, consider a considerable factor of safety on loads as the poles are manufactured in un-monitored conditions
The pole shall be erected such that minimum 1/6th of the total length of the pole shall be embedded into the ground surface
Which of the following is not the type of Pole Foundation :
Rectangular
Circular
Pyramidal
None
Which of the following is not Minor Equipment :
LA
CT
HG Fuse
Isolator
Which of the following is not Major Equipment :
AB Switch
VCB
Transformer
HG Fuse
Which of the following is type of Transformer Foundation:-
Pedestal Type
Block Type
Both of the above
None
For Thermal Expansion and Contraction and to resist Sway Caused by Wind in Boundary Wall :-
Expansion joint at Every 2‐5 m
Expansion joint at Every 4‐8 m
Expansion joint at Every 12‐15 m
None
Which of the following is not the type of Road :
Flexible Pavement
Rigid Pavement
WBM Road Foot Path
Wooden Pavement
What is WBM Road Foot Path :-
Water Bound Macadam
Water Below Main Road
Water Between Main Road
Water Bounded by main road
ELECTRICAL CONDUITS should be laid :-
AFTER PLASTERING
AFTER PAINTING COMPLETED
DURING BRICK WORK
NONE