13 questions
Identify the longest task?
Fill Kettle
Boil Kettle
Put tea in cup
Put sugar in cup
Get milk out of fridge
How many tasks are dependent on pouring water into a cup?
1
2
4
5
How many seconds form the critical path?
100 seconds
220 seconds
205 seconds
120 seconds
200 seconds
What is Critical Path Analysis
A project management technique for process planning that defines critical (milestones) and non-critical tasks
A graphical display of project activities represented by an area of land showing physical features
A set of drawings which consists of floor plan, site plan, and landscape drawings for the ease of construction at site
A colourful diagram, displaying a visual representation of total spending against the time taken to complete a project
Which are the activities that immediately preceded activity I?
E
K
F
H
What is the earliest event time for event 4?
4 days
4 hours
4 minutes
4 weeks
What is the latest event time for event 2?
2 days
3 days
4 days
5 days
What is the total float for activity B?
0 days
1 day
2 days
3 days
What is the total float for activity H?
4 days
5 days
6 days
7 days
Which are the critical activities?
C
F
K
A
What is the minimum completion time for the project?
15 days
10 days
20 days
17 days
Activity J is delayed by 4 days. What is the minimum completion time for project following this delay?
15 days
16 days
18 days
19 days