What is the goal of the pi planning event
Create a plan for the upcoming PI showing how stories mapt to iterations
Achieve alignment on what needs to and can be built
buils a release roadmap
identify the risks in the upcoming features using a ROAMing exercise
What best supports innovation in the SAFe House of Lean
Visualizing work
Built-in quality
Fast Learning cycles
Optimizing the whole
on the seventh day of the iteration, the team realizes that they wil not complete 5 of the 13 stories. The product owner (PO) says she cannot negotiate the scope of the remaining stories any further. What is the PO's best course of action?
Defer aceptance testing to the next iteration
Have an emergebncy iteration planning meeting
Stop the current iteration and plan a new iterartion with the new knowledge
Communicate the status of the iteration to all stakeholders
An agile team has which two characteristics? (choose two)
A group of dedicated individuals whe are empowered, self-organizing, self-managing, and deliver value
A large group of individuals who all work together to create value for the client
A small group of tipically 5-11 dedicated individuals who have the skills necessary to define, build, test, and deploy incréments of value
A stand-alone unit of individuals who do not require input from other teams to complete their tasks
A group of dedicated individuals that work in phase-gate steps to complete their PI objectives
What is the role of the product owner?
Estimate the stories in the product backlog
To represent the Customer to the agile team
to ensure quality by testing the solution
to priotirize the program backlog
Which situation should use the Large solution SAFe configuration?
Organizations that need to have system demos after each iteration
organizations that need to scale agile across the enterprise
organizations that operate in an environment that requires compliance for complex, high assurance systems
every large enterprise that uses SAFe
What is one responsability of the scrum master
to facilitate the pi planning session
to define the tasks and assign owners
to priotirize the team's backlog
to remove impediments in order to help protect the team
What is the major benefice of reducing batch siize
Increases work in process
Increases visibility
Increases throughtput
Decreases stress on the system
What information does a cumulative flow diagram provides
The self-assessment information for the teams
The cycle time system information which starts the implementation
The data for the team to identify current bottlenecks
The derived predictability data for the team
What type of visibility should Product Owners provide during the agile release Train Sync
Visibility into analysis, approval, and feature readiness for implementation
Visibility into scope and priority ajustments
Visibility intop programs Epics and features
Visibility into backlog items
Which activity happens in the inspect and Adapt workshop
Refining the program backlog
a demo for the integrated system
Planning the next PI
a retrospective for the iteration
Which statement describe the balance between emergent design and intentional architecture when talking about building quality?
It is required for speed of value delivery and Solution intent
it is required for implementation speed and maturity
it is required for backlog speed and designed refinement
it is required for speed of development and maintenability
Which is an example of a part of an iteration retrospective?
Program level analysis of a problem using root cause analysis techniques
Estimation of stories
gathering feedback from the stakeholders
Team Discussion around opportunities for continuous improvment
Which statement is true about iteration goals
They verify that teams are working at their fuull capacity
They are used to measure business value achieved for each iteration
They align team to a common vision of work in the iteration
They are used to track scope changes over time
What is recommended length for an iteration?
Ten weeks
Four weeks
Eight weeks
Two weeks
How does a team demonstrates progress?
By having the product owner verbally communicate to the stakeholders
by representing status sllides
By showing the actual working product
By showing screen shots of the product
Which statement is true about the purpose of a work in process constraint?
It identifies possible constraints for solution completion
It captures where all new "big" ideas come from
it helps analyse, approve, and track Portfolio Epics and Enablers
It encourages collaboration and enables flow
What type of information can be easily seen in a cumulative flow diagram
Time to complete a Feature
Work in process across the team
team capacity
the number of defects that escape to production
During the inspect and Adapt event, how are reflection, data collection, problem solving, and identification of improvment actions used?
To help the team bond and work more efficiently together
To increase the quality and reliability of the next PI
To evaluate better implementation steps
To enhance ans improve the innovation and planning practices
What should be taken into account when estimating Story point size?
Number of days it will take
Complexity
Priority
Team size
What does a program board help teams identify
Dependencies between teams
Program-level risks
Work breakdowns
Each teams tasks
What is one key benefit of a backlog refinement session
It is the main way in SAFe for achevieng relentless improvement
It provides time to identify dependencies and issues that could impact the next iteration
It serves a variety of purposes, including a dedicated time for planning, retrospecting, exploring, and innovating
It allows th eteam to state the problemeand think about what, where, when and the impact
What is one of the six steps in the problem solving workshop
Choose a problem to solve--agreement not required
Identify the biggest root cause using the Pareto analysis
Brainstorm possible failures
Apply root solution analysis
Which statement defines the purpose of iteration planning?
It is to analyse, approve, and ready Features for implementation
It is to break Stories into tasks that are achievable in the team's capacity
It is to organize the work and define a realistic scope for the iteration
It is to explore and implement program Epics and split them into features to be further explored
Product Management is responsible for "what get built" as defined by the vision, Roadmap, and what else
key stakeHolders
PI Planning
Program backlog
Customers
What is one of the recommended way of splitting features into stories during a PI planning event?
Implement the simplest variant of the functionality first and the implement the rest as an enhancement
Develop the functionality first and then test it on a second pass
Implement the database structure first and then implement the business logic and user interface
Develop the User interface (UI) with sample business logic and database access and then add the actual functionality behind the UI
Which two statements best describe elements of continuous delivery? (Choose two)
Development and test environments should be separate from production
Automate testing Features and nonfunctional requirements
Deploy to staging every third iteration
Maintain manual deployment
Maintain a staging environment that emulates production
What are three practices of Extreme Programming (XP)? (Choose three.)
Continuous integration
Pair programming
Deployment automation
intentional architecture
Test-driven development
The release train engineer is a servant leader who displays which two actions or behaviors? (Choose two)
Identifies market needs
Leads by example
Establishes Feature accceptance criteria
Listen and supports teams in problem identification and decision-making
Owns vision and Roadmaps, Program Backlog and ROI
When is the System Demo conducted during program execution?
When the System Team is ready
Each week
Only when all stakeholders are available
At the end of every iteration
The daily stand-up timebox should not exceed how many minutes?
20 minutes
5 minutes
10 minutes
15 minutes
Which statement is true about pair work in the scaled agile Framework?
it is for developers only
It comes from pair programming in Extreme Programming (XP)
It occurs during iteration planning
it is a best practice that team members should spend 50 % to 100% of the time in pair work
A decrease in variability leads to an increase in what
Autonomy
Options
Innovation
Predictability
Which process guides the final approval for a release in SAFe?
Product Management
Continuous Delivery Pipeline
Lean Portfolio management
Release Governance
Which statement is true about iteration Planning
The PO does not need to attend
Items are assigned to the eteam members
It occurs on the last day of the iteration
It is required for every iteration to enable fast Learning cycles
Which statement describes a cross-functional team
Each team member can do all activities to define, build and test a solution
Each team member can define and build, with a system team testing the solution
Each team can deliver Features across multiple domains
Each team member can define, build, and test a component feature
The scrum masterwants to establish a team's initial Velocity. A team has two tester, three developpers, one full time Scrum Master, and a Product owner split between two teams. What is their normalized Velocity before calculating for time off?
40
48
32
52
A team finishes developing all of their stories in the first six days of the iteration, test them in the Following two days, and fixes bugs in the days remaining. How is the team bahaving?
They are ignoring nonfunctional requirements within the iteration
They are applying the agile development Practice of "separation of concerns"
They are waterfailing the iteration
They are abusing the practice of hardening
A user story includes which three things? (Choose three.)
Definition of done
What
Why
How
Who
What is scrum?
A routine method of deploying deliverables to operations
A methodology used to deliver usable and reliable solutions to the end user
A lightweight process for cross-functional, self organizing teams
A process for continuosly maintaining deployment readiness
What are two behaviors of an effective Scrum master? (Choose two)
To guarantee no changes are made to the scope during an iteration
Facilitate more than two teams
Facilitate the PI planning session
To act as a servant leader and xhibit Lean-agile leadership
To facilitate the team's progress toward the iteration goals
Which statement describes the information within a story?
A story is written in full detailed spécifications so that the work is ready to be implemented immediately
No further conversation is required after the story is identified because it contains all necessary details
story acceptance criteria must be finalized before beginning iteration planning
A story provides just enough information for the intent to be understood by both business and technical people
Which two statements describe an agile release train?(Choose two)
It identifies when too much work is in the system which result in multitasking and frequent context switching
It is a long-lived, self organizing, virtual organization of 5-12 agile teams tha plan, commit, and execute together
It is the primary value delivery construct in the Scaled Agile Framework
It is used to describe large system behaviors that fulfill Custome needs
It shows the deliverables for the currently commited PI and offers visibility into the next two PIs
The CALMR approach to DevOps includes Automation, Lean Flow, Measurement, and Recovery. What does the "C" represent?
Cadence
Culture
Cycle-Time
Continuous integration