In which of the following project phases is the project schedule developed?
Conceptual
Planning
Implementation
Design
2. Multiple Choice
30 seconds
1 pt
To crash a schedule you should:
Increase the time allowed on those tasks that have float.
Try to invest more time on tasks that are behind schedule
Replace the team members that are not performing well
Put extra resources on the tasks that are on critical path.
3. Multiple Choice
30 seconds
1 pt
Completion of the successor activity depends upon the completion of its predecessor activity.
start-to-start
start-to-finish
finish-to-start
finish-to-finish
4. Multiple Choice
30 seconds
1 pt
The inputs used in the Define Activities process includes all BUT
Scope baseline
Milestone List
EEF
OPA
5. Multiple Choice
30 seconds
1 pt
The successful project managers spend most of their time:
Planning with their personnel
Planning with the top management
Communication with the project team
Studying project results
6. Multiple Choice
30 seconds
1 pt
Which of the following is the output of the Plan Schedule Management process?
Activity list
Schedule Management Plan
Milestone list
Project Schedule Network Diagram
7. Multiple Choice
30 seconds
1 pt
Free float can be determined
any time after activity durations have been estimated
once the total float for a network path has been calculated
as soon as all activities are defined
none of these
8. Multiple Choice
30 seconds
1 pt
A sequence of tasks that cannot be delayed without causing the project to be completed late.
Float
Critical path
Milestone
Payback period
9. Multiple Choice
30 seconds
1 pt
What type of diagram shows planned and actual project schedule information?
a tracking Gantt chart
a Gantt chart
a network diagram
a milestone chart
10. Multiple Choice
30 seconds
1 pt
Activity Resource Requirements is an input to which of the following processes?
Control schedule
Estimate Activity Durations
Estimate Activity Resources
Sequence activities
11. Multiple Choice
30 seconds
1 pt
Abdullah, a project manager is identifying and documenting relationships among the project activities of an IT project. He is undertaking which of the following process?
Define Activities
Develop Schedule
Sequence Activities
Estimate Activity Durations
12. Multiple Choice
30 seconds
1 pt
The method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS is known as: