No student devices needed. Know more
10 questions
The following are essential ingredients of a valid contract except _________.
counteroffer
offer and acceptance
consideration
intention to create legal relationship
The following are factors that vitiates a contract except ___________.
illegal contracts
consideration
misrepresentation
duress
Under the PSSCOC, the contractor is issued with _______ when the works are substantially completed.
completion certifcate
certificate of substantial completion
variation order
delay certificate
The following are factors to consider when selecting standard forms of contract except the___________.
length of the contract
nature of the contractual relationship intended by the parties
general characteristics of the work
client’s preference
Which one of the following tendering methods is suitable for tenders that involve sensitive work installation?
Open tenders
Selective tenders
Limited tenders
Small value purchase
Under the SIA contract, when a construction project is completed, the architect is required to issue the _________.
certificate of substantial completion
completion certificate
extension of time certificate
delay certificate
When a Superintending Officer orders a Contractor to do additional works, he has to order a/an __________.
direction
instruction
statement
schedule
Under the SIA contract, a/an _________ is given to the Contractor to secure compliance.
instruction
direction
certificate
request for proposal
In a typical construction project, the main contract is signed between the ________ and the ________.
architect; main contractor
architect; subcontractor
employer; architect
employer; main contractor
Under the SIA contract, if the investigation result shows that a Contractor had not complied with contract requirement, the architect has to issue a ______ to order the contractor to rectify the Works.
Direction
Instruction
payment certificate
completion certificate
Explore all questions with a free account