What is the main reason that we do projects?
We have free time on our hands.
Make new friends.
Add value to our organizations by changing the status quo.
My boss wants me to do it to make his KPI better.
Which is NOT part of project management process groups?
Close
Action
Plan
Initiate
In the Stakeholder's map, what are we assessing the stakeholders on?
Influence & Power
Influence & Interest
Interest & Credibility
Credibility & Power
Which is one of the main role of a project sponsor?
Authorizes the project charter
Chairs all project meetings
Leads the project
Collects Stakeholder's requirement
Which is NOT a part of project objective statement?
Scope
Risk
Resources / cost
Schedule
What is Work Breakdown Structure?
A Gantt Chart with timeline
Organization of project deliverables into smaller components
A schedule
A project charter
Which of the following best describe the critical path?
Tasks with the highest risk
Longest time the project will take from start to finish
Path with the most uncertainty
Scope that is most important
In risk management plan, we reduce the risk by reducing the ...
budget and speed
speed and impact
likelihood and impact
speed and scope
Which of the followings is NOT a way to optimize your project?
Explain the reason for not meeting the deadline
Re-assign resources
Do tasks concurrently
Break dependencies
What is the action you should take when you are given unrealistic timeline?
Threatened to resign
Just proceed at your own pace and ignore this requirement
Show the plan with the estimated time for each task
Complain to your co-workers (who doesn't vent, right?)