35 questions
During the conceptual phase of a pipeline project, the project engineer estimates the following: the cost of the materials is most likely $100,000; optimistically $90,000; and pessimistically $120,000. The cost for labor is most likely $80,000; optimistically $70,000 and pessimistically $100,000. The cost for equipment is most likely $60,000; optimistically $50,000 and pessimistically $70,000. The cost for construction management fees is most likely $30,000; optimistically $20,000 and pessimistically $40,000. What is the probability of the project coming in under $270,000?
Less than 50%
Exactly 50%
Over 50%
Zero
An activity has an early start (ES) of day3; a late start (LS) of day 13, an early finish (EF) of day 9 and a late finish (LF) of day 19. What is the duration of this activity?
3
10
7
6
Based on the following, if you needed to shorten the duration of the project, which activity would you try to shorten?
Activity B
Activity D
Activity H
Activity C
Based on the chart below, some of the identified risks do not occur and therefore activity B gets done in 3. What is the effect on the project?
The Project is Complete
There will be Three Critical Path
Activity A will have more Float
The project will complete sooner if activity F start immediately