Project cost management

Project cost management

Assessment

Assessment

Created by

Trâm Anh

Mathematics

University

18 plays

Hard

Improve your activity

Higher order questions

Match

Reorder

Categorization

Quizizz AI

actions

Add similar questions

Add answer explanations

Translate quiz

Tag questions with standards

More options

5 questions

Show answers

1.

Multiple Choice

1 min

1 pt

If Earned Value (EV) = 350, Actual Cost (AC) = 400, Planned Value (PV) = 325, what is Cost Variance (CV)?

350

- 75

400

-50

2.

Multiple Choice

2 mins

1 pt

You are a project manager working on a project that requires 100 items to be tested, spaced evenly over five weeks. you have just begun week three, with an overall budget of us $10,000. to date, you have spent us $2,000 with 40 items tested successfully. what does the cost variance (cv) tell you in this circumstance?

The project is proceeding at 100% of the expected rate.

The project is $2000 under budget.

The project is on budget.

The project is getting $2 of work for every dollar spent.

3.

Multiple Choice

1 min

1 pt

A project team budgeted us $3,000 for the work performed and has spent us $4,000 to date. if they budgeted us $5,000 for the work sccheduled, what is the cost variance (cv)?

($1,000)

$2,000

$1,000

($2,000)

4.

Multiple Choice

1 min

1 pt

A Cost Performance Index (CPI) of 0.89 means?

At this time, we expect the total project to cost 89 percent more than planned

When the project is completed we will have spent 89 percent more than planned

The project is only progressing at 89 percent of the rate planned

The project is only getting 89 cents out of every dollar invested

5.

Multiple Choice

2 mins

1 pt

You are managing a project which is into six months of its execution. You are now reviewing the project status and you have ascertained that project is behind schedule. The actual cost of Activity A is ₹ 2,00,000 and that of Activity B is ₹ 1,00,000. The planned value of these activities are ₹ 1,80,000 and ₹ 80,000 respectively. The Activity A is 100% complete. However, Activity B is only 75% complete. Calculate the cost performance index of the project on the review date.

0.7

0.8

0.9

0.6

cartoon woman

Explore this activity with a free account

Find a similar activity

Create activity tailored to your needs using

Quizizz AI
Two Step Equations

13 questions

Two Step Equations

assessment

7th Grade

Multi Step Equations

10 questions

Multi Step Equations

assessment

8th - 12th Grade

Shapes

10 questions

Shapes

assessment

KG - 2nd Grade

Direction & Coordinates

15 questions

Direction & Coordinates

assessment

3rd Grade

Solving Equations

27 questions

Solving Equations

lesson

8th - 10th Grade

Research Design

23 questions

Research Design

lesson

12th Grade

Solving Multistep Equations

25 questions

Solving Multistep Equations

assessment

9th - 11th Grade