25 questions
_______________________ consists of all technical and managerial activities required to deliver the deliverables to the client.
A software project has a specific ____________, consumes _____________ and produces ___________________.
Which of the following will be mentioned in the project agreement?
scope
duration
cost
deliverables
delivery dates
__________ is the work products that will be delivered to the client.
__________ is the work products that will be delivered to the client.
Which of the following are considered deliverables?
Demonstration of function
Demonstration of non functional requirements
Demonstration of subsystems
Demonstration of requirements from client
______________ is the activity or set of activities that span the duration of the project.
_____________ is the smallest unit of work subject to management.
____________ is the major unit of work with precise dates.
Which of the following are the activities during requirements analysis?
Refine scenarios
Define use case model
Define object model
Design user interface
________________ involves the processes required to ensure timely completion of a project.
Which of the following is the processes for project time management?
Activity definition
Activity sequencing
Activity duration estimating
Schedule development
_______________ includes start and end dates and budget information of a project.
______________________ involves developing a more detailed WBS and supporting explanations to understand all the work to be done so you can develop realistic duration estimates.
_____________________ involves relationships between project and non-project activities.
Mandatory dependencies
Discretionary dependencies
External dependencies
Critical path dependencies
_____________________ are the preferred technique for showing activity sequencing.
__________________ means task (B) cannot finish until task (A) finishes
Finish-to-start (FS)
Start-to-start (SS)
Finish-to-finish (FF)
Start-to-finish (SF)
When determine duration estimation, we need to include the actual amount of time worked on an activity plus ________________.
Which of the following are the tools and techniques for schedule development?
Gantt chart
PERT analysis
critical path analysis
critical chain scheduling
_____________ are significant events on a project that normally have zero duration.
__________________ is work done before transition to reduce the effect of problem.
Which of the following is the strategies for risk reduction
Avoiding the risk
Transferring the risk
Assuming the risk
Escape from risk
Which of the following is the strategies for software change?
Software Maintenance
Architectural transformation
Software Re-engineering
Risk transfer
_______________________ is general process of changing a system after it has been diverted.
Which of the following are types of maintenance?
Maintenance to repair software faults
Maintenance to the logic of systems
Maintenance to adapt software to a different operating environment
Maintenance to add to or modify the system's functionality