Identify the longest task?
Fill Kettle
Boil Kettle
Put tea in cup
Put sugar in cup
Get milk out of fridge
How many milestones are there?
6
7
8
9
10
How many tasks are dependent on pouring water into a cup?
1
2
3
4
5
How many seconds form the critical path?
100 seconds
220 seconds
205 seconds
120 seconds
200 seconds
What is Critical Path Analysis
A project management technique for process planning that defines critical (milestones) and non-critical tasks
A graphical display of project activities represented by an area of land showing physical features
A set of drawings which consists of floor plan, site plan, and landscape drawings for the ease of construction at site
A colourful diagram, displaying a visual representation of total spending against the time taken to complete a project